Draft Capital Outturn
Meeting: 29/06/2009 - Cabinet (Item 7)
7 Draft Capital Programme Outturn 2008-09 PDF 179 KB
Report of the Director of Finance and Support
Additional documents:
- 07 Capital Prog Outturn Rpt Appx1, item 7
PDF 33 KB
- 07 Capital Prog Outturn Rpt Appx 2, item 7
PDF 32 KB
- 07 Capital Prog Outturn Rpt Appx 3, item 7
PDF 38 KB
Decision:
The following is noted:
1. The outturn position for the Council’s capital programme for 2008-09 and how the expenditure was financed.
2. The slippage of unfinished schemes from 2008-09 into the 2009-10 capital programme, and how the planned expenditure is to be funded.
3. Funding issues arising in 2009-10 as a result of capital receipts shortfalls in 2008-09.
Minutes:
Councillor Perkins, as relevant Portfolio Holder, submitted a report advising of the outturn expenditure and funding position for the Council’s Capital Programme for 2008/09 and the slippage of unfinished schemes and unapplied funding from 2008/09 into the Council. He drew attention to an item of slippage caused by a delay in the completion of the roofing contract owing to a contractor going out of business. It was further pointed out that the refurbishment of Abington Park Museum was subject to a grant of external funding.
RESOLVED
That Cabinet note:
1. The outturn position for the Council’s capital programme for 2008-09 and how the expenditure was financed.
2. The slippage of unfinished schemes from 2008-09 into the 2009-10 capital programme, and how the planned expenditure is to be funded.
3. Funding issues arising in 2009-10 as a result of capital receipts shortfalls in 2008-09.