Capital Programme Monitoring 2009-10 Period 5: Project Appraisals and Variations
Meeting: 04/11/2009 - Cabinet (Item 11)
11 Capital Programme Monitoring 2009-10 Period 5: Project Appraisals and Variations PDF 184 KB
B Report of the Director of Finance
Additional documents:
- 11B Capital Mon rptAppdxA, item 11
PDF 204 KB
- 11B Capital Mon rptAppdxB, item 11
PDF 50 KB
- 11B Capital Mon rptAppdxC, item 11
PDF 34 KB
- 11B Capital Mon rptAppdxD, item 11
PDF 23 KB
- 11B Capital Mon rptAppdxE, item 11
PDF 28 KB
Decision:
1. The following variations to schemes in the capital programme for 2009-10 are approved.
Scheme Reference, Description & Directorate |
Narrative |
2009-10 £ |
Future Years £ |
Funding Source |
2007-08/PR0010 V01 Hot Property
Housing GF |
This project is funded by NBC, utility companies and private landlords. Contributions to the value of £5,351 have been received in 2009-10; therefore the budget for this project needs to be increased by this amount. |
5,351 |
- |
Third party contributions |
2008-09/GF066 V01 Sport & Recreation in Beckets Park
Planning & Regeneration |
Phase one of this project was completed in 2008-09 which included installing children’s play equipment that met DDA requirements, to improve access to play for children with disabilities, and a 5 a side football pitch. It was the intention that more works would take place improving the environment of Beckets Park, but it is now felt this would conflict with the strategic improvement of Beckets Park. |
(13,121) |
- |
Section 106 |
2009-10/GF026 V02 GOEM Project Decent Homes
Housing GF |
The budget for this project was based on an estimate of the amount of external grant funding that would be received for works to decent homes in the private sector. The amount of funding received was £258,424 more than the estimate; therefore the budget needs to be increased by this amount. |
258,424 |
- |
GOEM Grant |
Further details of these variations can be seen at Annex A of the report.
2. The following is noted
a. The capital programme monitoring position is noted as at end of August 2009, including forecast outturns and slippage into 2010-11, as set out at Annex B and C.
b. The funding arrangements for the 2009-10 capital programme as set out at Annex E.
Minutes:
Councillor Clarke addressed Cabinet expressing concern at the £250K overspend on bringing private landlord properties up to standard. However he was pleased to see the overspend for disabled adaptations, as this showed that vulnerable people were getting their needs addressed. He did suggest that there was something very wrong with budget forecasting to have misjudged the spending to this extent.
Councillor Mildren addressed Cabinet, commenting on the expenditure outlined in Annex B of the report and enquiring if the £300K capitalisation directive related to potential employee costs as set out in Annex D.
Councillor Perkins, as Portfolio Holder for Finance, presented the report to cabinet and took members through the details of the proposed variations as laid out in the appendices to the report.
Councillor PD Varnsverry and Councillor Beardsworth stressed the importance of ensuring that housing adaptations for vulnerable people were carried out at the earliest opportunity. Councillor B Hoare added that a large proportion of the work had been necessary to cover a baglog left by previous administrations in spite of insufficient funding coming from central Government.
RESOLVED
1. That the following variations to schemes in the capital programme for 2009-10 be approved.
Scheme Reference, Description & Directorate |
Narrative |
2009-10 £ |
Future Years £ |
Funding Source |
2007-08/PR0010 V01 Hot Property
Housing GF |
This project is funded by NBC, utility companies and private landlords. Contributions to the value of £5,351 have been received in 2009-10; therefore the budget for this project needs to be increased by this amount. |
5,351 |
- |
Third party contributions |
2008-09/GF066 V01 Sport & Recreation in Beckets Park
Planning & Regeneration |
Phase one of this project was completed in 2008-09 which included installing children’s play equipment that met DDA requirements, to improve access to play for children with disabilities, and a 5 a side football pitch. It was the intention that more works would take place improving the environment of Beckets Park, but it is now felt this would conflict with the strategic improvement of Beckets Park. |
(13,121) |
- |
Section 106 |
2009-10/GF026 V02 GOEM Project Decent Homes
Housing GF |
The budget for this project was based on an estimate of the amount of external grant funding that would be received for works to decent homes in the private sector. The amount of funding received was £258,424 more than the estimate; therefore the budget needs to be increased by this amount. |
258,424 |
- |
GOEM Grant |
Further details of these variations can be seen at Annex A of the report.
2. That the following be noted
a. The capital programme monitoring position is noted as at end of August 2009, including forecast outturns and slippage into 2010-11, as set out at Annex B and C.
b. The funding arrangements for the 2009-10 capital programme as set out at Annex E.