1.      The following schemes are to be to be added to the capital programme for 2009-10.

 

Scheme Reference, Description

&

Directorate

Narrative

2009-10

£

Future

Years

£

Funding Source

2009-10/GF070 Grimebusters

 

Environment & Culture

Purchase of two trailer mounted pressure washers and a bespoke vehicle for street washing and gum removal. The vehicle and equipment would be used to deliver an enhanced street scene with washed streets (targeting the town centre), free of gum and a reduction in graffiti.

84,000

-

NEIP

2009-10/GF071B Carbon Management Projects – Lighting and Timeclocks

 

Environment & Culture

To undertake a range of energy saving projects to reduce the carbon emissions of the Council, in line with the adopted policy and terms and conditions of the external grant funding.  The work will include lighting upgrades to: Greyfriars bus station, Westbridge Cedos block, Camp Hill Depot and Fish Street offices. Timeclocks will be installed at the Central Museum, Fish Street offices and Westbridge Admin block. Passive infrared lighting will be installed at Lings Forum.

52,721

-

50% Prudential Borrowing, 50% Salix

2009-10/GF072 Partnership Information Hub (GIS)

 

Finance & Support

To create a Northamptonshire partnership information hub. This will ensure that there is a comprehensive central information point for demographic, socio-economic and general geographic information.

121,000

49,000

NEIP

 

Further details of these appraisals can be seen at Annex A of this report.

 

 

2.      The following variations to schemes in the capital programme for 2009-10 are approved.

 

Scheme Reference, Description

&

Directorate

Narrative

2009-10

£

Future

Years

£

Funding Source

Budget Increase

2008-09/GF073 V03 Money 4 Youth

 

Assistant Chief Executive

Additional funding of £25k has been awarded to NBC for floodlights and a youth shelter at the multi-use games area in St Davids. The original budget for this project was an estimate of the funding that would be received, the amount in the capital programme is £14,632 less than the funding received, therefore the budget needs to be increased by a net amount of £10,368.

10,368

-

GOEM

Budget Decrease

2009-10/GF063B V01 Lings Forum Lighting Upgrade

 

Environment & Culture

Further testing has shown that this project is not compliant with the terms and conditions of the Salix funding. Other projects will be submitted to utilise this funding, therefore there are no savings as a result of this variation.

(39,444)

-

50% Prudential Borrowing, 50% Salix

Neutral Budget Impact

2007-08/CS012 V06 Kitchen Replacement (Backlog)

 

Housing HRA

Additional kitchens requiring urgent replacement and kitchens that are in homes in a general poor state of repair have resulted in the average kitchen cost being higher than estimated.

80,000

-

MRA

2008-09/HRA007 V04 Complete Roofs

 

Housing HRA

An additional roof replacement arising out of a responsive repair issue required capital replacement over and above this year’s original programme.

45,000

-

MRA

2009-10/HRA002 V02 Cooper Street Heating Improvements – Phase 2

 

Housing HRA

This project has been tendered and has come in well within budget. Sizeable contingencies are required to ensure all the technical issues associated with a complex district heating scheme can be resolved quickly and efficiently, to  ...  view the full decision text for item 10

Minutes:

Councillor Clarke addressed cabinet and reiterated an earlier comment that these monitoring reports referred to real people.  He was not confident that the Council could achieve what had been promised and was particularly concerned about a promise of an updated heating system that had not been delivered. He repeated his concern about the lack of service in communal areas.

 

In response, the Portfolio Holder for Housing agreed to discuss details of Councillor Clarke’s specific concerns outside of the meeting. It had generally been felt inappropriate during this cold weather to perform works that could leave people without heating, even for a short time.

 

Councillor Perkins presented the report to Cabinet. He assured members that all schemes set out in the report were fully funded and progress was as would be expected at this stage of the financial year.  It was made clear that forecast saving was against the original capital plan and there was still money available to finish all current projects in the appropriate way.

 

RESOLVED

1.      That the following schemes be to be added to the capital programme for 2009-10.

 

Scheme Reference, Description

&

Directorate

Narrative

2009-10

£

Future

Years

£

Funding Source

2009-10/GF070 Grimebusters

 

Environment & Culture

Purchase of two trailer mounted pressure washers and a bespoke vehicle for street washing and gum removal. The vehicle and equipment would be used to deliver an enhanced street scene with washed streets (targeting the town centre), free of gum and a reduction in graffiti.

84,000

-

NEIP

2009-10/GF071B Carbon Management Projects – Lighting and Timeclocks

 

Environment & Culture

To undertake a range of energy saving projects to reduce the carbon emissions of the Council, in line with the adopted policy and terms and conditions of the external grant funding.  The work will include lighting upgrades to: Greyfriars bus station, Westbridge Cedos block, Camp Hill Depot and Fish Street offices. Timeclocks will be installed at the Central Museum, Fish Street offices and Westbridge Admin block. Passive infrared lighting will be installed at Lings Forum.

52,721

-

50% Prudential Borrowing, 50% Salix

2009-10/GF072 Partnership Information Hub (GIS)

 

Finance & Support

To create a Northamptonshire partnership information hub. This will ensure that there is a comprehensive central information point for demographic, socio-economic and general geographic information.

121,000

49,000

NEIP

 

Further details of these appraisals could be seen at Annex A of the Cabinet report.

 

 

2.      That the following variations to schemes in the capital programme for 2009-10 be approved.

 

Scheme Reference, Description

&

Directorate

Narrative

2009-10

£

Future

Years

£

Funding Source

Budget Increase

2008-09/GF073 V03 Money 4 Youth

 

Assistant Chief Executive

Additional funding of £25k has been awarded to NBC for floodlights and a youth shelter at the multi-use games area in St Davids. The original budget for this project was an estimate of the funding that would be received, the amount in the capital programme is £14,632 less than the funding received, therefore the budget needs to be increased by a net amount of £10,368.

10,368

-

GOEM

Budget Decrease

2009-10/GF063B V01 Lings Forum Lighting  ...  view the full minutes text for item 10