Capital Programme Monitoring, Project Appraisals and Variations - December 2009
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Decision:
1. The following variations to schemes in the capital programme for 2009-10 are approved.
Scheme Reference, Description & Directorate |
Narrative |
2009-10 £ |
Future Years £ |
Funding Source |
|
Budget Increase |
|||||
2007-08 GI0009 V03 E-Payments Chip & Pin
Finance & Support |
There were unforeseen complications during the project, which resulted in the need for additional resource to ensure project deadlines were met. The E-returns did not work when they went live, which meant that each individual E-return had to be rebuilt. The additional budget required will be funded by an increase in prudential borrowing. |
4,103 |
- |
Prudential Borrowing |
|
2008-09/GF045B V05 CMP Building Energy Management System
Environment & Culture |
An increase in budget is necessary due to additional work being required. The unallocated Salix grant funding and prudential borrowing that is ringfenced for carbon management projects will fund this. |
673 |
- |
50% Salix Grant, 50% Prudential Borrowing |
|
Budget Decrease |
|||||
2008-09 GF036 V06 & 2009-10 GF066 V01 CMP Pipework Insulation
Environment & Culture |
Pipework insulation has been completed at Lings Forum, Mounts Baths, Danes Camp Leisure Centre and the Guildhall. The cost of all of these pieces of work are less than originally thought, therefore the budgets need to be reduced. There will be no savings arising from this variation; the funding will be reinvested in other carbon management projects, in line with the terms and conditions of the external funding. |
(4,374) |
- |
50% Salix Grant, 50% Prudential Borrowing |
|
2009-10/GF057 V01 Danes Camp Flume Relining
Environment & Culture |
A supplier has been found that can carry out the project in a method that causes little disruption to the pool’s timetable therefore eliminating the necessity to close. The project costs are also much less than originally budgeted for which reduces the amount of capital funding required.
|
(8,000) |
- |
GF Revenue Contribution |
|
Movement Between Years |
|||||
2008-09/GF057 V01 Upton Country Park Pedestrian & Cycle Bridge
Planning & Regeneration |
The delivery of the project is delayed due to a third party land ownership issue and incorrect base data provided by the Environment Agency. The original cost estimate did not have a sufficient allowance for the necessary temporary works and access costs to construct the bridge. The revised cost has been compiled with input from a civil engineering contractor. |
(654,000) |
1,321,217 |
Section 106 |
|
2009-10/GF067 V01 Camp Hill MUGA
Environment & Culture |
Due to construction lead times and time to source materials being longer than originally stated, construction will now take place next financial year. |
(47,150) |
47,150 |
The Big Lottery |
|
2009-10/HRA002 V03 Cooper Street Heating Improvements Phase 2
Housing HRA |
As a result of the recent severe weather conditions and the outcome of the risk assessment undertaken, works on this project will not be completed this financial year. It is proposed to slip £586,640 into next financial year, so that works can carry be completed in warmer weather, when tenants will not require their heating. |
(586,640) |
586,640 |
MRA |
|
2009-10/HRA004 V06 Decent Homes & Poor Condition
Housing HRA |
Slippage into next financial year is required due to contract start date on site being later than initially planned. |
(765,000) |
765,000 |
HRA Earmarked Reserve, MRA & RTB Capital Receipts |
|
2009-10/HRA005 V03 Garage Roofs & Doors
Housing HRA |
A garage review is underway, identifying the sites for improvement or development. It is not appropriate to carry out works until the review is complete and the overall position on garages has been assessed. It is therefore requested to slip the remaining budget for this project into next financial year in order to fulfil the works highlighted from the review. |
(21,882) |
21,882 |
MRA |
|
2009-10/HRA009 V02Environmental Enhancements
Housing HRA |
This project was slow to start due to: 1) Issues with residents consultation. 2) Design of schemes. 3) Leaseholder consultation. Therefore not all of the budget will be spent in 2009-10 and it is proposed to move £24,520 into 2010-11. |
(24,520) |
24,520 |
MRA |
|
2009-10/HRA013 V03Adhoc Doors & Window Replacements
Housing HRA |
Slippage is required into the next financial year due to planned works being delayed because of the severe weather conditions during December and January. |
(12,000) |
12,000 |
MRA |
|
2009-10/HRA015 V03 Lifts Refurbishment
Housing HRA |
The start date of this project was delayed due to issues with section 20 notices. Works will start this financial year, but will not be completed until 2010-11. |
(130,000) |
130,000 |
MRA |
|
Further details of these variations can be seen at Annex A of this report.
2. The following is noted:
a) The capital programme monitoring position as at end of December 2009, including forecast outturns, revenue expenditure funded by capital and slippage into 2010-11, as set out at Annex B, C and D.
b) The funding arrangements for the 2009-10 capital programme as set out at Annex E.
Publication date: 11/02/2010
Date of decision: 10/02/2010
Decided at meeting: 10/02/2010 - Cabinet
Effective from: 17/02/2010