Capital Programme (Monitoring Report)

Decision Maker: Cabinet

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

1.      Approval is given for the scheme as set out in Paragraph 2.1 of Item 11C of the Cabinet Agenda to be added to the capital programme for 2009-10.

Further details of the appraisal can be seen at Annex A of the same report.

 

2.      Approval is given for the variations to schemes in the capital programme for 2009-10 as outlined in Paragraph 2.2 of item 11C of the Cabinet Agenda. Further details of these variations can be seen at Annex B of the same report.

 

3.      It is noted that:

 

a)     The capital programme monitoring position as at end of September 2009, including forecast outturns, revenue expenditure funded by capital and slippage into 2010-11, as set out at Annex C, D and E of the report presented to Cabinet.

 

b)     The funding arrangements for the 2009-10 capital programme as set out at Annex F of the report presented to Cabinet.

Publication date: 26/11/2009

Date of decision: 25/11/2009

Decided at meeting: 25/11/2009 - Cabinet

Effective from: 02/12/2009